Core Knowledge · Multimode systems
For this pharmacy outage drill, usable battery energy is 9 kWh and the backed-up load is a steady 600 W. Ignore solar recharge and ignore extra conversion losses, as the drill instructions say. How long can that load run?
Answer choices
a
5.4 hours, because 9 times 0.6 is the runtime and division is the wrong operation.
b
15 hours, because 9 kWh divided by 0.6 kW equals 15.
c
0.015 hours, because 9 kWh divided by 600 W should be left in those mixed units without converting.
d
5400 hours, because 9 kWh times 600 is the runtime of a steady backup load.
Next question