The executive who controls the budget wants a one-page milestone note and has asked not to be invited to daily standups. They can stop the project, and they are not asking for detail. How should they be engaged?
Answer choices
a
Monitor only, the same way you would a distant observer with no stake
b
Manage closely with a standing daily invitation
c
Keep them satisfied with the concise milestone note they asked for, and escalate exceptions
d
Remove them from the register because they declined the standup