Process · Schedule
Design and build are currently finish-to-start. The team proposes starting build before design finishes, with no extra staff. What does that change do?
Answer choices
a
It is crashing: cost goes up and risk stays the same
b
It removes risk because the two teams will see each other’s work sooner
c
It is fast tracking: duration may drop and rework risk goes up
d
It adds float to the critical path by definition