Process · Planning
The next month is planned in tasks. The quarter after that is milestones only, because a vendor design is not chosen yet. A stakeholder calls the milestone-only quarter a failure to plan. What is it?
Answer choices
a
Rolling-wave planning: near work is detailed, later work stays coarse until information exists
b
Scope creep, because later work is not fully decomposed
c
Gold plating, because milestones add unrequested scope
d
An abandoned schedule baseline