People · Stakeholders
A department two business units away has no interface with this project, no budget role, and no users in scope. They asked only to be told if that ever changes. What level of engagement fits?
Answer choices
a
Manage closely, with a weekly working session
b
Monitor, and contact them if the interface appears
c
Keep satisfied with a monthly steering deck
d
Treat them as owners of the backlog