  "examSlug": "nabcep-pva",
  "examCode": "PVA",
  "examName": "NABCEP Photovoltaic Associate",
  "outline": {
    "title": "NABCEP Photovoltaic Associate Job Task Analysis V.2026.2",
    "effective": "April 2026 JTA (exam content from 7 April 2026)",
    "url": "https://www.nabcep.org/resource/pv-associate-jta/"
  },
  "domains": [
    { "id": "safety", "name": "Safety", "weight": 20 },
    { "id": "core", "name": "Core Knowledge", "weight": 20 },
    { "id": "sales", "name": "Sales and Economics", "weight": 10 },
    { "id": "design", "name": "Design", "weight": 18.3 },
    { "id": "install", "name": "Installation", "weight": 18.3 },
    { "id": "om", "name": "Operations and Maintenance", "weight": 13.4 }
  ],
  "topics": [
    {
      "slug": "exam-format",
      "domainId": "safety",
      "outlineRef": "Exam characteristics",
      "question": "How is the NABCEP PV Associate exam structured?",
      "answer": "The PV Associate exam is 70 multiple-choice items, 60 of them scored, with a 2-hour limit and a scaled passing score of 65. Ten items are unscored pilots. Field Guide’s draft practice set is original study material mapped to the April 2026 job-task analysis. It is not a NABCEP form, and it has not had a Crosscheck pass. Confirm the current handbook on nabcep.org before you register.",
      "citation": {
        "label": "NABCEP Associate program — PV Associate exam characteristics",
        "url": "https://www.nabcep.org/certifications/associate-program/"
      }
    },
    {
      "slug": "hierarchy-of-controls",
      "domainId": "safety",
      "outlineRef": "Domain I, Task 1",
      "question": "What does the hierarchy of controls mean on a PV crew?",
      "answer": "The hierarchy runs from elimination and substitution, through engineering controls and administrative controls, down to PPE. A harness is real protection and it is still the last layer: if the work can be done on the ground, that elimination outranks another toolbox talk. Fall protection at 6 feet, lockout of every source, and a rescue plan before anyone ties off sit in the same safety domain. Field Guide drills on this page are original drafts, not NABCEP items.",
      "citation": {
        "label": "NABCEP PVA JTA V.2026.2 — Safety, hierarchy of controls",
        "url": "https://www.nabcep.org/resource/pv-associate-jta/"
      }
    },
    {
      "slug": "system-types",
      "domainId": "core",
      "outlineRef": "Domain II, Task 1",
      "question": "Which PV system types does the 2026 core domain name?",
      "answer": "The core domain names PV-direct (a load that runs only while the array is lit, with no battery and no grid), stand-alone, grid-tied, and multimode (grid-tied with storage that can also back up selected loads). A plain grid-tied inverter must stop energizing utility conductors when the grid fails. That anti-islanding behavior is not a backup system. Field Guide’s core drills are original drafts mapped to those four types.",
      "citation": {
        "label": "NABCEP PVA JTA V.2026.2 — Core Knowledge, system types",
        "url": "https://www.nabcep.org/resource/pv-associate-jta/"
      }
    },
    {
      "slug": "stc-and-temperature",
      "domainId": "core",
      "outlineRef": "Domain II, electrical concepts",
      "question": "What are STC, and what does cell temperature do to voltage?",
      "answer": "Standard Test Conditions are 1000 W/m², a 25 °C cell, and an AM 1.5 spectrum. On crystalline silicon, the voltage coefficient is negative, so Voc and Vmp fall as the cell heats and rise in the cold. Isc moves only slightly the other way. String design uses the cold rise for the maximum-voltage check and the hot drop for the MPPT-window check. Nameplate watts are not the watts you get on a 65 °C roof.",
      "citation": {
        "label": "NABCEP PVA JTA V.2026.2 — Core Knowledge, STC and temperature",
        "url": "https://www.nabcep.org/resource/pv-associate-jta/"
      }
    },
    {
      "slug": "savings-claims",
      "domainId": "sales",
      "outlineRef": "Domain III",
      "question": "What should a PV savings claim be tied to?",
      "answer": "Tie dollars to the actual tariff, the site’s azimuth, tilt, and shade, and a stated degradation assumption. Export credit might be retail net metering, net billing, or avoided cost; it is not one national rate. A federal tax credit, when it applies, reduces income-tax liability for qualified costs. It is not a check handed over on install day, and eligibility belongs with a tax adviser and the current statute. An assumed utility-rate escalator is not a guarantee. These Field Guide notes are draft study material, not a NABCEP sales script.",
      "citation": {
        "label": "NABCEP PVA JTA V.2026.2 — Sales and Economics",
        "url": "https://www.nabcep.org/resource/pv-associate-jta/"
      }
    },
    {
      "slug": "permission-to-operate",
      "domainId": "sales",
      "outlineRef": "Domain III, interconnection",
      "question": "When may a new system operate in parallel with the utility?",
      "answer": "After the utility issues permission to operate. A finished install and a filed application are not that permission. Closing the PV breaker early, or backfeeding through another meter, is still unauthorized parallel operation. Field Guide’s practice set treats permission to operate as a sales-and-economics constraint because it changes what the customer can be promised on day one.",
      "citation": {
        "label": "NABCEP PVA JTA V.2026.2 — Sales and Economics, interconnection",
        "url": "https://www.nabcep.org/resource/pv-associate-jta/"
      }
    },
    {
      "slug": "string-window",
      "domainId": "design",
      "outlineRef": "Domain IV, string sizing",
      "question": "What two temperature checks size a series string?",
      "answer": "In the cold, string Voc must stay at or under the inverter’s maximum DC input and the code voltage limit (600 V DC on one- and two-family dwellings under the 2023 NEC). In the heat, string Vmp must stay inside the MPPT window. Using STC voltage for both checks misses the cold rise and the hot drop. Field Guide’s design drills walk those two edges with the coefficient printed in the item. Confirm the code edition the authority having jurisdiction enforces.",
      "citation": {
        "label": "NEC 2023 690.7 and inverter MPPT limits; NABCEP PVA JTA design domain",
        "url": "https://www.nabcep.org/resource/pv-associate-jta/"
      }
    },
    {
      "slug": "load-side-120",
      "domainId": "design",
      "outlineRef": "Domain IV, interconnection",
      "question": "How does the 120% allowance limit a load-side PV breaker?",
      "answer": "On a load-side connection, 120% of the bus rating must cover the main breaker plus the PV breaker. A 200 A bus with a 200 A main leaves 40 A for PV. If that breaker is too small and the load calculation will not allow a smaller main, a supply-side connection is one remaining path, subject to the service equipment and the utility. Field Guide teaches the arithmetic as a draft drill. The adopted NEC edition and the utility’s interconnection rule decide the job.",
      "citation": {
        "label": "NEC 2023 705.12 load-side busbar allowance",
        "url": "https://www.nfpa.org/codes-and-standards/nfpa-70-standard-development/70"
      }
    },
    {
      "slug": "listed-connectors",
      "domainId": "install",
      "outlineRef": "Domain V, wiring",
      "question": "Which module connectors are allowed to mate in the field?",
      "answer": "Only a listed mating pair. Two housings that look alike and come from different brands are not a pair unless that combination is listed. Vinyl tape and an exposed wire nut are not connectors. Exposed rooftop source-circuit conductors are USE-2 or listed PV wire, not NM cable. Field Guide’s installation drills are original drafts keyed to those listing limits.",
      "citation": {
        "label": "NEC 2023 690.33 and 690.31",
        "url": "https://www.nfpa.org/codes-and-standards/nfpa-70-standard-development/70"
      }
    },
    {
      "slug": "commissioning-checks",
      "domainId": "install",
      "outlineRef": "Domain V, commissioning",
      "question": "Which checks happen before a new string inverter is turned on?",
      "answer": "Confirm polarity before the DC disconnect closes, and compare measured Voc with the temperature-corrected expectation. About half the expected Voc means modules are missing from the series string or a section is bypassed. Insulation resistance is measured with the string isolated, not while the inverter is exporting. Torque on clamps is the listed value, read with a tool. These are Field Guide draft drills, not a manufacturer’s commissioning sheet.",
      "citation": {
        "label": "NABCEP PVA JTA V.2026.2 — Installation, commissioning",
        "url": "https://www.nabcep.org/resource/pv-associate-jta/"
      }
    },
    {
      "slug": "half-current",
      "domainId": "om",
      "outlineRef": "Domain VI, monitoring",
      "question": "A string suddenly makes about half the current of its neighbors. Is that soiling?",
      "answer": "No. Soiling tends to pull neighboring strings down together and gradually. A hard drop to about half on one string points at an open, a blown fuse, a failed connector, or a failed module-level device. A slow even loss of a few percent over several years can be ordinary aging. A one-day step change is a fault. Field Guide’s O&M drills keep those two patterns apart.",
      "citation": {
        "label": "NABCEP PVA JTA V.2026.2 — Operations and Maintenance, monitoring",
        "url": "https://www.nabcep.org/resource/pv-associate-jta/"
      }
    },
    {
      "slug": "fault-lockouts",
      "domainId": "om",
      "outlineRef": "Domain VI, troubleshooting",
      "question": "What should happen when an inverter locks out on a ground fault or a repeating arc fault?",
      "answer": "Leave the protective function in place, lock out the sources, and find the fault. Defeating a ground-fault detector, jumpering an arc-fault circuit, or resetting all day leaves a damaged conductor energized. A blank monitoring portal with a normal inverter display is a communications problem, not the same fault. Field Guide practice items on these trips are original drafts and are not NABCEP exam questions.",
      "citation": {
        "label": "NABCEP PVA JTA V.2026.2 — Operations and Maintenance, troubleshooting",
        "url": "https://www.nabcep.org/resource/pv-associate-jta/"
      }
    }
  ]
}