  "examSlug": "pmp",
  "examCode": "PMP",
  "examName": "Project Management Professional",
  "outline": {
    "title": "PMI Project Management Professional (PMP) certification page, July 2026 exam",
    "effective": "Public certification page for the July 2026 exam. This draft bank is not weighted to that mix.",
    "url": "https://www.pmi.org/certifications/project-management-pmp"
  },
  "domains": [
    { "id": "people", "name": "People", "weight": 33 },
    { "id": "process", "name": "Process", "weight": 41 },
    { "id": "biz", "name": "Business Environment", "weight": 26 }
  ],
  "topics": [
    {
      "slug": "domain-weights",
      "domainId": "people",
      "outlineRef": "Examination content",
      "question": "How is the PMP exam split across People, Process, and Business Environment?",
      "answer": "PMI’s public certification page for the July 2026 exam lists People 33 percent, Process 41 percent, and Business Environment 26 percent. About 40 percent of items are predictive and about 60 percent are agile or hybrid. The sitting is 180 questions, of which 10 are unscored pretest items, in 240 minutes (4 hours), with two 10-minute breaks. This Fieldguide draft is not that mix. It is a legacy-weighted study set on the pre–July 2026 outline: 40 People, 48 Process, and 8 Business Environment items. Those counts follow the old 42 / 50 / 8 proportions and have not been rebalanced. The timed 180-item attempt stays off. Fieldguide is not affiliated with the Project Management Institute. These pages are study notes, not PMI items.",
      "citation": {
        "label": "PMI — PMP certification page (July 2026 exam: 180 questions, 4 hours, People 33 / Process 41 / Business Environment 26)",
        "url": "https://www.pmi.org/certifications/project-management-pmp"
      },
      "citations": [
        {
          "label": "PMI — July 2026 PMP Examination Content Outline (170 scored, 10 pretest, 240 minutes, about 60% agile or hybrid)",
          "url": "https://www.pmi.org/-/media/pmi/documents/public/pdf/certifications/new-pmp-examination-content-outline-2026.pdf"
        }
      ]
    },
    {
      "slug": "manage-conflict",
      "domainId": "people",
      "outlineRef": "People — conflict",
      "question": "When should a project manager collaborate, force a decision, or step back from a conflict?",
      "answer": "Use the mode that fits the stake and the clock. Collaborate, or problem-solve, when the issue matters to both sides and there is time to work the merits. Direct or force a decision when safety, a legal duty, or an outage cannot wait, then review it after the emergency. Step back when the issue is trivial. A quick compromise or a smooth-over is a partial yield, not a substitute for looking at a real design tradeoff. Cross-cultural friction belongs in the team’s working agreement, not in a rule that one culture is unprofessional. Fieldguide is not affiliated with PMI.",
      "citation": {
        "label": "PMI — PMP certification (People domain is part of the public exam description)",
        "url": "https://www.pmi.org/certifications/project-management-pmp"
      }
    },
    {
      "slug": "stakeholders-and-virtual-teams",
      "domainId": "people",
      "outlineRef": "People — stakeholders and teams",
      "question": "How do power and interest change the way you engage someone, including on a virtual team?",
      "answer": "High power and high interest is managed closely. High power and low interest is kept satisfied with the short cadence they will actually read. Low power and high interest is kept informed, especially the people who will use the result. Low power and low interest is monitored. Update the assessment when a stance changes. A virtual team also needs a written decision log, a rotating overlap so one region is not always excluded, and local holidays on the calendar. A hallway “sure” on a shared person is not a resource commitment until dates and the time split are on the calendar. Fieldguide is not affiliated with PMI.",
      "citation": {
        "label": "PMI — PMP certification",
        "url": "https://www.pmi.org/certifications/project-management-pmp"
      }
    },
    {
      "slug": "earned-value",
      "domainId": "process",
      "outlineRef": "Process — cost and schedule performance",
      "question": "Which earned-value formulas tell cost from schedule, and which estimate-at-completion formula matches the assumption?",
      "answer": "Cost performance index is earned value divided by actual cost. Schedule performance index is earned value divided by planned value. Below 1 is over budget or behind schedule. Cost variance is earned value minus actual cost. Schedule variance is earned value minus planned value. If the current cost index is expected to continue, estimate at completion is budget at completion divided by the cost performance index. If the overrun was one time, estimate at completion is actual cost plus the remaining budgeted work, which is budget at completion minus earned value. The to-complete performance index against the original budget is remaining work divided by remaining budget. These are standard project-control definitions used as study drills. Fieldguide is not affiliated with PMI.",
      "citation": {
        "label": "PMI — PMP certification (Process domain is part of the public exam description)",
        "url": "https://www.pmi.org/certifications/project-management-pmp"
      }
    },
    {
      "slug": "schedule-and-critical-path",
      "domainId": "process",
      "outlineRef": "Process — schedule",
      "question": "What makes a path critical, and how do float, crashing, and fast tracking differ?",
      "answer": "The critical path is the longest path through the network. It sets the shortest project duration. Total float is late start minus early start, or late finish minus early finish. Free float is the successor’s early start minus this activity’s early finish. Crashing spends money or people to shorten the critical path. Shortening an activity that has float does not move the end date. Fast tracking overlaps work that was in sequence and raises rework risk. Resource leveling may move the finish date. Resource smoothing stays inside float and keeps the finish date. The PERT weighted duration is (optimistic + 4 times most likely + pessimistic) divided by 6. Fieldguide is not affiliated with PMI.",
      "citation": {
        "label": "PMI — PMP certification",
        "url": "https://www.pmi.org/certifications/project-management-pmp"
      }
    },
    {
      "slug": "risk-change-and-procurement",
      "domainId": "process",
      "outlineRef": "Process — risk, change, and procurement",
      "question": "How should a project manager treat a threat, a baseline change, and a contract that does not match the scope?",
      "answer": "Threat responses are avoid, mitigate, transfer, and accept. Escalate when the only useful response sits outside the project manager’s authority. Residual risk remains after a response. A secondary risk is created by the response. A workaround is an unplanned action when no specific plan existed. An issue is happening now and gets an owner. Contingency reserve covers identified risks inside the cost baseline. Management reserve covers unidentified work and needs the approval your governance names. On a predictive baseline, analyze a change before the baseline moves. A bid far under an independent estimate needs a clarification before award. Unclear discovery paid by the hour fits time and materials with a ceiling, not a firm fixed price. Fieldguide is not affiliated with PMI.",
      "citation": {
        "label": "PMI — PMP certification",
        "url": "https://www.pmi.org/certifications/project-management-pmp"
      }
    },
    {
      "slug": "agile-roles",
      "domainId": "process",
      "outlineRef": "Process — agile and hybrid",
      "question": "Who owns the product backlog, and what is the difference between a review and a retrospective?",
      "answer": "In Scrum, the product owner is accountable for maximizing the value of the product and for ordering the product backlog. Developers own how the increment is built and select the sprint work with the product owner. The scrum master coaches the process and helps remove impediments. A sprint review inspects the increment with stakeholders. A retrospective inspects how the team worked, including after a review that went well. The definition of done is the shared quality bar for an increment. Acceptance criteria belong to one story. A hybrid project can keep a compliance stage gate and still build software in short increments. The Scrum Guide is the public source for these Scrum accountabilities. Fieldguide is not affiliated with PMI or with Scrum.org.",
      "citation": {
        "label": "The Scrum Guide (CC BY-SA 4.0)",
        "url": "https://scrumguides.org/scrum-guide.html"
      }
    },
    {
      "slug": "compliance-and-benefits",
      "domainId": "biz",
      "outlineRef": "Business Environment — compliance and value",
      "question": "What should happen when a law, a benefit metric, or a strategy change cuts across the plan?",
      "answer": "A law already in effect outranks a date preference. Show the impact and offer legal choices such as cutting scope, moving the date, or adding capacity. Do not skip the control or backdate a record that was not performed. Work that does not move the funded benefit is a candidate to defer, with the reason visible. A live system is an output. If the benefit was adoption, a healthy server does not mean the benefit landed. When a merger or another external change removes the strategy that justified the work, take a continue, pivot, or stop recommendation back to the sponsor. Fieldguide is not affiliated with PMI.",
      "citation": {
        "label": "PMI — PMP certification (Business Environment is part of the public exam description)",
        "url": "https://www.pmi.org/certifications/project-management-pmp"
      }
    },
    {
      "slug": "not-affiliated",
      "domainId": "biz",
      "outlineRef": "About this draft",
      "question": "Is this PMP practice written or endorsed by PMI?",
      "answer": "No. Fieldguide is an independent study site. This draft is a legacy-weighted study set on the pre–July 2026 outline (40 People, 48 Process, 8 Business Environment). It is not the current PMI domain mix (People 33, Process 41, Business Environment 26, about 60 percent agile or hybrid). It has not had a Crosscheck pass. It is not a PMI item bank, not a promise of a passing score, and not affiliated with the Project Management Institute. Confirm eligibility, fees, and the current exam content outline on PMI’s own site before you apply.",
      "citation": {
        "label": "PMI — Project Management Professional (PMP) certification",
        "url": "https://www.pmi.org/certifications/project-management-pmp"
      }
    }
  ]
}