Who owns the product backlog, and what is the difference between a review and a retrospective?

In Scrum, the product owner is accountable for maximizing the value of the product and for ordering the product backlog. Developers own how the increment is built and select the sprint work with the product owner. The scrum master coaches the process and helps remove impediments. A sprint review inspects the increment with stakeholders. A retrospective inspects how the team worked, including after a review that went well. The definition of done is the shared quality bar for an increment. Acceptance criteria belong to one story. A hybrid project can keep a compliance stage gate and still build software in short increments. The Scrum Guide is the public source for these Scrum accountabilities. Fieldguide is not affiliated with PMI or with Scrum.org.

The Scrum Guide (CC BY-SA 4.0)