Which earned-value formulas tell cost from schedule, and which estimate-at-completion formula matches the assumption?

Cost performance index is earned value divided by actual cost. Schedule performance index is earned value divided by planned value. Below 1 is over budget or behind schedule. Cost variance is earned value minus actual cost. Schedule variance is earned value minus planned value. If the current cost index is expected to continue, estimate at completion is budget at completion divided by the cost performance index. If the overrun was one time, estimate at completion is actual cost plus the remaining budgeted work, which is budget at completion minus earned value. The to-complete performance index against the original budget is remaining work divided by remaining budget. These are standard project-control definitions used as study drills. Fieldguide is not affiliated with PMI.