What makes a path critical, and how do float, crashing, and fast tracking differ?
The critical path is the longest path through the network. It sets the shortest project duration. Total float is late start minus early start, or late finish minus early finish. Free float is the successor’s early start minus this activity’s early finish. Crashing spends money or people to shorten the critical path. Shortening an activity that has float does not move the end date. Fast tracking overlaps work that was in sequence and raises rework risk. Resource leveling may move the finish date. Resource smoothing stays inside float and keeps the finish date. The PERT weighted duration is (optimistic + 4 times most likely + pessimistic) divided by 6. Fieldguide is not affiliated with PMI.
Same domain
- Which earned-value formulas tell cost from schedule, and which estimate-at-completion formula matches the assumption?
- How should a project manager treat a threat, a baseline change, and a contract that does not match the scope?
- Who owns the product backlog, and what is the difference between a review and a retrospective?