How should a project manager treat a threat, a baseline change, and a contract that does not match the scope?
Threat responses are avoid, mitigate, transfer, and accept. Escalate when the only useful response sits outside the project manager’s authority. Residual risk remains after a response. A secondary risk is created by the response. A workaround is an unplanned action when no specific plan existed. An issue is happening now and gets an owner. Contingency reserve covers identified risks inside the cost baseline. Management reserve covers unidentified work and needs the approval your governance names. On a predictive baseline, analyze a change before the baseline moves. A bid far under an independent estimate needs a clarification before award. Unclear discovery paid by the hour fits time and materials with a ceiling, not a firm fixed price. Fieldguide is not affiliated with PMI.